2022 Pavement Rehabilitation Project

Project Description:

The 2022 Pavement Rehabilitation project encompasses a comprehensive scope of pavement rehabilitation, pedestrian facility enhancements, and drainage improvements. Utilizing the full-depth reclamation (FDR) method, this initiative will effectively reconstruct the street, ensuring a service life of at least 20 years. The FDR method is a highly sustainable pavement rehabilitation technique that integrates advanced technologies and material recycling processes. By minimizing greenhouse gas emissions through reduced truck usage, it significantly lowers the environmental impact and the overall cost of pavement maintenance.

Project Timeline:

 

Following the Notice to Proceed issued on June 6th, 2024, the 2022 Pavement Rehabilitation Project commenced on June 10th, 2024. The project is scheduled for completion within 120 working days, with an expected finish date of December 2nd, 2024.

Construction Management Firm, Filippin Engineering, will provide updated three-week look-ahead schedules to ensure the project timeline remains current. To view  latest schedule, please use: 2022 Pavement Rehabilitation Project Three-Week Look-Ahead for PDF download or see below for more information.

Monday, September 2nd, 2024 – Friday, September 20th, 2024:

3 week look ahead 09-04-24

*Please note that the schedule is subject to change in events or circumstances beyond Contractor/City control.*

 

Project Location:

 

Street Name Block Begin Limit End Limit
Byrnes Lane 1200 End Cameo Road
Callejon Drive 5500 Concha Loma Drive End
Cameo Road 5500 La Brea Lane Casitas Pass Road
Cramer Circle1 1200 1275 Cramer Circle 1234 Cramer Circle
Dorrance Way 4700 Ash Avenue Holly Avenue Intersection
Dorrance Way 4700 to 4800 Holly Avenue Intersection Elm Avenue
Dorrance Way 4900 Elm Avenue Linden Avenue
El Carro Lane 4500 to 4600 Santa Ynez Avenue Azalea Drive Intersection
El Carro Lane 4700 Azalea Drive Intersection Sterling Avenue
Fourth Street2 4500 to 4700 Holly Avenue End
Kathy Street 1500 Dariesa Street End
Lisa Street 1500 Dariesa Street End
Myra Street 1500 Dariesa Street End
Retorno Drive 5500 Concha Loma Drive South end
Star Pine Road3 5300 East end Vallecito Road
Vallecito Road 1000 to 1100 North end Carpinteria Avenue
Via Real 4000 to 4100 Cravens Lane 4200 Via Real

1 Minor storm drain improvements only.

2 Colored mountable curb only for consistency with Third Street and Dorrance Way.

3 Pavement rehabilitation and Vallecito Road and Star Pine Road intersection minor storm drain improvements.

Project Map:

 

El Carro Lane

Vallecito Road, Star Pine Road, Byrnes Lane, Cameo Road

Via Real

Kathy Street, Lisa Street, Myra Street

Callejon Drive, Retorno Drive

Dorrance Way

 

Staff Contact:

 

John L. Ilasin, Public Works Director/City Engineer

Email: johni@carpinteriaca.gov