Project Description:
The 2022 Pavement Rehabilitation project encompasses a comprehensive scope of pavement rehabilitation, pedestrian facility enhancements, and drainage improvements. Utilizing the full-depth reclamation (FDR) method, this initiative will effectively reconstruct the street, ensuring a service life of at least 20 years. The FDR method is a highly sustainable pavement rehabilitation technique that integrates advanced technologies and material recycling processes. By minimizing greenhouse gas emissions through reduced truck usage, it significantly lowers the environmental impact and the overall cost of pavement maintenance.
Project Timeline:
Following the Notice to Proceed issued on June 6th, 2024, the 2022 Pavement Rehabilitation Project commenced on June 10th, 2024. The project is scheduled for completion within 120 working days, with an expected finish date of December 2nd, 2024.
Construction Management Firm, Filippin Engineering, will provide updated three-week look-ahead schedules to ensure the project timeline remains current. To view latest schedule, please use: 2022 Pavement Rehabilitation Project Three-Week Look-Ahead for PDF download or see below for more information.
Monday, September 2nd, 2024 – Friday, September 20th, 2024:
*Please note that the schedule is subject to change in events or circumstances beyond Contractor/City control.*
Project Location:
Street Name | Block | Begin Limit | End Limit |
Byrnes Lane | 1200 | End | Cameo Road |
Callejon Drive | 5500 | Concha Loma Drive | End |
Cameo Road | 5500 | La Brea Lane | Casitas Pass Road |
Cramer Circle1 | 1200 | 1275 Cramer Circle | 1234 Cramer Circle |
Dorrance Way | 4700 | Ash Avenue | Holly Avenue Intersection |
Dorrance Way | 4700 to 4800 | Holly Avenue Intersection | Elm Avenue |
Dorrance Way | 4900 | Elm Avenue | Linden Avenue |
El Carro Lane | 4500 to 4600 | Santa Ynez Avenue | Azalea Drive Intersection |
El Carro Lane | 4700 | Azalea Drive Intersection | Sterling Avenue |
Fourth Street2 | 4500 to 4700 | Holly Avenue | End |
Kathy Street | 1500 | Dariesa Street | End |
Lisa Street | 1500 | Dariesa Street | End |
Myra Street | 1500 | Dariesa Street | End |
Retorno Drive | 5500 | Concha Loma Drive | South end |
Star Pine Road3 | 5300 | East end | Vallecito Road |
Vallecito Road | 1000 to 1100 | North end | Carpinteria Avenue |
Via Real | 4000 to 4100 | Cravens Lane | 4200 Via Real |
1 Minor storm drain improvements only.
2 Colored mountable curb only for consistency with Third Street and Dorrance Way.
3 Pavement rehabilitation and Vallecito Road and Star Pine Road intersection minor storm drain improvements.